Milestone
Final Design Documents
Final Construction Drawings
Material Procurement
Wall & Floor Panel Construction (prefabricated offsite)
LHPOST6 Construction (start*)
Instrumentation
Seismic Test Phases
Live Fire Test Phases
* pending facility access
Target (Start) Date
January 2024
March 2024
ongoing – June 2024
April – June 2024
July 2024
December 2024 – February 2025
March 2025
May 2025