Schedule

Milestone

Final Design Documents

Final Construction Drawings

Material Procurement

Wall & Floor Panel Construction (prefabricated offsite)

LHPOST6 Construction (start*)

Instrumentation

Seismic Test Phases

Live Fire Test Phases

* pending facility access

Target (Start) Date

January 2024

March 2024

ongoing – June 2024

April – June 2024


July 2024

December 2024 – February 2025

March 2025

May 2025